Pageloader

South-Side Utility Tunnel

/, Metal Works/South-Side Utility Tunnel
Qatar South-Side Utility Tunnel

Client: Qatar Petrolum

Date: 01-03-2010

Estimation: QAR 12.7 Million

Duration: 2 Years

Project Description: 

  • 340 Ton G.I External Pipe Support.
  • 8650 LMI External Access Ladder Epoxy Coat Finish.
  • 6430 M2 PVC Membrane Car Shed.
  • 9000 LM I Trench Cover.
  • 199 Fire Rated Doors.
  • Owner: Qatar Foundation
  • Consultant: KEO
  • Contractor: Zublin Internaional Qatar