Mesaieed Housing Project Package 4
Category: Architectural Design, General Construction, Metal Works, Residential
Client: Qatar Real Estate Investment Company
Date: 28-01-2015
Estimation: QAR 10.53 Million
Duration: 2 Years
Tags: Building, Residential
Project Description:
Design, Manufacturing, Painting and Installing of:
- 6425 LMI Internal Steel Handrail Epoxy Coat Finish.
- 4500 M2I External Steel Pergola Epoxy Coat Finish.
- 1030 M2I External Service Gates Epoxy Coat Finish.
- 4325 LMI External Access Ladder Epoxy Coat Finish.
- 1700 LMI Boundary Wall Fence Epoxy Coat Finish.
- 8575 M2 PVC Membrane Car Shed.
- Owner: Qatar Petrolum – Mesaieed Industrial City
- Consultant: MUNSELL/AECOM
- Contractor: Zublin International Qatar